Every restaurant opening has two calendars: the one on the construction schedule, and the one the furniture actually follows. When they diverge, you get the classic opening-week scramble — a finished dining room with folding chairs in it, or a delayed opening burning rent with no revenue. This guide walks through how the FF&E fabrication pipeline really works, where owners lose time without realizing it, and how to plan backward from an opening date.
Quick answer: Custom restaurant furniture moves through five stages — design, shop drawings, fabrication, finishing, and installation — and the total runs weeks to months, not days. The most common mistake is treating seating as a late purchase, like smallwares. Custom booths, banquettes, and millwork should be released early in the project so fabrication runs parallel to construction, with installation landing in the window after floors and paint but before staff training.
The Pipeline: Design to Install
1. Design and Selection
Layout, dimensions, materials, and finishes get decided. For seating, this includes upholstery selection — and if the designer is specifying COM (customer’s own material), the clock on mill lead times starts here. Decisions left open at this stage do not delay this stage; they delay every stage after it.
2. Shop Drawings
The fabricator translates design intent into dimensioned fabrication drawings, verifies field conditions, and submits for approval. This stage is sequential — fabrication should not start until drawings are approved — so approval turnaround time is schedule time. An owner or architect who sits on a submittal for weeks has quietly moved the opening date.
3. Fabrication
Frames get built, parts get CNC-cut, metalwork gets welded, foam gets cut and fitted, upholstery gets sewn and applied. In a one-shop operation like Lion Craft’s Phoenix facility — millwork, metalwork, upholstery, stone, and lighting under one roof — these tracks run in parallel. Split across vendors, they often run in sequence, because vendor B waits on vendor A’s output.
4. Finishing
Stain, conversion varnish, catalyzed lacquer — applied in controlled spray conditions with proper cure time between coats. Finishing is chemistry and cannot be compressed by urgency. Rushed finishing is the most visible corner ever cut: it is the bar top that hazes and the table edge that chips in month two.
5. Delivery and Installation
Furniture ships and crews install. Lion Craft runs its own install crews across the Southwest and nationally, which removes a coordination seam — the people installing the booths are from the shop that built them, so field surprises get solved on the spot rather than escalated between companies.
What Owners Get Wrong
- Ordering seating last. The single most common error. Owners sequence spending in construction order — walls, then mechanicals, then finishes — and treat furniture as a finishing touch. But custom seating has a pipeline as long as many construction phases. It belongs in the first wave of releases, not the last.
- Confusing catalog lead times with custom lead times. A catalog chair ships from a warehouse. A custom booth run does not exist until it is drawn, approved, and built. The quoted timeline starts at drawing approval — not at the first phone call.
- Slow submittal approvals. Every week a shop drawing sits unapproved is a week added to the end of the schedule.
- Changing materials mid-stream. A material swap after fabrication starts can send the schedule back two stages.
Long-Lead Items to Release First
Some items consistently carry the longest pipelines and should be released earliest:
- Custom booths and banquettes — drawing, structure, foam, and upholstery all stack. Release custom seating at the front of the project.
- Bar packages — bar dies, back bars, and stone or solid-surface tops involve the most trade coordination in the room.
- COM fabric — see below.
- Anything with specialty materials — imported stone, specific hardwood species, custom metal finishes.
Shorter-lead items — catalog chairs, tabletops on standard bases, host stands in standard materials — still deserve early ordering, but they are not usually what breaks the schedule.
How COM Fabric Affects the Timeline
COM — customer’s own material — means the designer specs fabric from an outside mill and ships it to the fabricator. It delivers a signature look, and it adds a dependency the fabricator does not control: the mill’s own lead time. If the fabric arrives late, upholstery waits, no matter how finished the frames are. The fix is simple: select and order COM at design sign-off, confirm yardage with the fabricator from the shop drawings, and have the mill ship directly to the shop. COM ordered early costs nothing extra in time; COM ordered late is a bottleneck wearing a designer label.
Working Backward From Your Opening Date
Build the FF&E schedule in reverse:
- Opening day — and note that staff training needs the dining room set before this.
- Installation window — after floors and paint, before final inspections and training.
- Fabrication and finishing block — working weeks, confirmed by your fabricator for your actual scope.
- Shop-drawing and approval block — including your own approval turnaround, honestly estimated.
- Release date — whatever date the arithmetic lands on. If it is earlier than you expected, that is the point.
Then add margin, because construction schedules move and the furniture pipeline should not be the thing with zero slack.
Start the Clock Early
The cheapest schedule insurance on a build-out is releasing FF&E early. If you have an opening date and a floor plan, request an estimate — we will map your scope against a realistic fabrication timeline and tell you when the release dates actually need to land.